PMP Exam Set G – Q67

Your project team has recently identified a risk in the software development project and decided not to change the project management plan to deal with the risk. The risk response strategy your team used in this scenario is an example of:

A. Mitigate
B. Transfer
C. Avoid
D. Acceptance

D. Acceptance