PMP Exam Set G – Q78

You are a project manager who is in charge of an important project for your company. The project is 40% complete after 3 months and has cost $350,000. The budget for the project is $950,000 and is scheduled to last 8 months. How is the project performing?

A. The project is behind schedule and over budget.
B. The project is ahead of schedule and under budget
C. The project is behind schedule and under budget.
D. The project is ahead of schedule and over budget

B. The project is ahead of schedule and under budget