PMP Exam Set E – Q95 ( PMBOK 6th edition )

You are an experienced project manager and have managed several data center migration projects. You are currently conducting training on the databases, spreadsheets and management plans you will be using during the lifecycle of the project. This training is a tool and technique in what process?

A. Manage Team
B. Acquire Resources
C. Develop Team
D. Control Quality

C. Develop Team

PMP Exam Set D – Q69 ( PMBOK 6th edition )

A project manager has scheduled technical training for her project team members in order to increase their skills. During which of the following processes these trainings will be delivered to the team members?

A. Manage Quality
B. Acquire Resources
C. Develop Team
D. Plan Resource Management

C. Develop Team