PMP Exam Set E – Q91

The development of requirements in the Collect Requirements process begins with an analysis of the information contained in the _______________ and _______________.

A. Project charter, Stakeholder register
B. Scope baseline, Requirements traceability matrix
C. Scope baseline, Stakeholder register
D. Project charter, Project scope statement

A. Project charter, Stakeholder register

PMP Exam Set C – Q74

Midway through the Collect Requirements process, a project manager finds that there are lots of unresolved issues. Which of the following is usually the best way to discover and resolve issues?

A. Interviewing
B. Use of a stakeholder register
C. Questionnaires
D. Facilitated workshops

D. Facilitated workshops

PMP Exam Set B – Q89

Which of the following is not a tool and technique of the Collect Requirements process?

A. Group creativity techniques
B. Interviews
C. Questionnaires
D. Traceability matrix

D. Traceability matrix