PMP Exam Set C – Q56

Peter is managing the development of an ecommerce website for his organization. Peter enjoys coercive powers and has assigned Julie, a project team member, to facilitate the team meetings. During any team meeting, Julie must?

A. Influence team members to support the project manager’s decisions
B. Support the team members to challenge the project manager’s decisions
C. Negotiate with team members to achieve the project objectives
D. Remain neutral and facilitate the meetings

D. Remain neutral and facilitate the meetings

PMP Exam Set A – Q27

Which of the following is NOT considered a method in the Manage Communications process?

A. Change control systems
B. Communication technology
C. Performance reporting
D. Information management systems

A. Change control systems