PMP Exam Set D – Q91 ( PMBOK 6th edition )

Peter is the project manager of an external project for a customer. The project is expected to take about a year to complete. Six months into the project, the customer informs Peter that the project needs to be scrapped. During which of the following processes would procedures be developed to handle early termination of a project?

A. Develop Project Charter
B. Close Project or Phase
C. Define Scope
D. Control Procurements

B. Close Project or Phase

PMP Exam Set C – Q15

What do buyers and seller have in common with regards to Control Procurements?

A. Each party ensures that both it and the other party meet their contractual obligations and that their own legal rights are protected.
B. Both parties have specific resources that can be idle.
C. Both parties have a contract change management plan.
D. Each party has its own project plan and legal team

A. Each party ensures that both it and the other party meet their contractual obligations and that their own legal rights are protected.