PMP Exam Set B – Q42

The Direct and Manage Project Work process has three tools and techniques. Two of them are Expert Judgment and Meetings. What is the third one?

A. Scheduling System
B. Configuration Management System
C. Project Management Information System
D. Change Control System

C. Project Management Information System

PMP Exam Set B – Q5

Which of the following is not an activity related to the Direct and Manage Project Work process?

A. Inspect the project deliverables for completeness.
B. Provide, train, and manage the team members assigned to the project.
C. Create project deliverables to meet the planned project work.
D. Perform activities to accomplish project objectives.

A. Inspect the project deliverables for completeness.