PMP Exam Set G – Q100

Jane has just started the Identify Stakeholders process for her project. She is currently looking for a template for the stakeholder register so that she doesn’t have to reinvent the wheel. Where can she find stakeholder register templates?

A. Organizational process assets
B. Project charter
C. Project management plan
D. Enterprise environmental factors

A. Organizational process assets

PMP Exam Set E – Q66

Emily is the project manager for a dam construction project. All project communications are recorded and documented for future reference. It has been decided that the project team will maintain last three months of project communication records at any given point in time. It has also been decided that the older communication records will be archived on a monthly basis. Where these records must be archived?

A. Change log
B. Organizational process assets
C. Enterprise environmental factors
D. Issue log

B. Organizational process assets