PMP Exam Set D – Q80

In a project, Activity A has a duration of 4 days and begins on the morning of Monday the 4th. The successor Activity, B, has a Finish-to-Start (FS) relationship with A. The Finish-to-Start relationship has 2 days of lag, and Activity B has a duration of 3 days. If Saturday and Sunday are non working days, which of the following statements is true?

A. Total elapsed days (completing both activities) is 7 days
B. Activity B will be completed by the end of day on Thursday, 14th
C. Activity B will be completed by the end of day on Friday, 15th.
D. Activity B will be completed by the end of day on Tuesday, 12th

B. Activity B will be completed by the end of day on Thursday, 14th