PMP Exam Set D – Q74

Public recognition of good performance creates positive reinforcement for the team members. When is the best time for a project manager to recognize team members’ performance?

A. During the lifecycle of the project
B. At the end of every phase of the project
C. At the end of the project
D. As mandated by the HR department.

A. During the lifecycle of the project

PMP Exam Set A – Q2

Your manager has asked you to include the Human Resource Management Plan and the Schedule Management Plan in your Project Management Plan. Is this the appropriate place for these items?

A. No, these are stand alone documents only.
B. Yes, you should unquestioningly include anything your manager suggests.
C. No, these documents should not be created until later in the project.
D. Yes, include them in the Project Management Plan.

D. Yes, include them in the Project Management Plan.