PMP Exam Set E – Q68 ( PMBOK 6th edition )

Which of the following is the process of communicating and working with stakeholders to meet their needs and expectations, address issues as they occur, and foster appropriate stakeholder engagement?

A. Manage Stakeholder Engagement
B. Monitor Stakeholder Engagement
C. Manage Communications
D. Monitor Communications

A. Manage Stakeholder Engagement

PMP Exam Set C – Q41 ( PMBOK 6th edition )

In an underground highway construction project, the project stakeholders have suggested many changes to the project scope. As you have already defined the cost baseline in your project, you would like to revisit the baseline to see how these changes impact the overall cost of the project. So, you have started an impact analysis to determine the impact, and inform the concerned stakeholders of all approved changes and the corresponding costs. You must use the following to carry out such process:

A. Control Scope
B. Monitor Risks
C. Control Costs
D. Monitor Communications

C. Control Costs