PMP Exam Set F – Q82 ( PMBOK 6th edition )

As part of risk planning, some responses are designed for use only if certain events occur. A project manager of a multi-year project decided to trigger one such set of responses during the Monitor Risks process. Which of the following is likely to have triggered the responses?

A. Late receipt of status reports
B. A key employee going on vacation for three days.
C. Errors found in a deliverable document
D. Missing an intermediate milestone

D. Missing an intermediate milestone

PMP Exam Set E – Q11 ( PMBOK 6th edition )

Identification of new risks, reassessment of old risks and closing of outdated risks are done as part of the Monitor Risks process. How often should project risk reassessment be scheduled?

A. It depends on how the project progresses relative to its objectives.
B. It is left to the discretion of the project manager.
C. Reassessment needs to be done at the 25%, 50%, and 75% stages of project completion.
D. Reassessment needs to be done at the 20%, 40%, 60% and 80% stages of project completion.

A. It depends on how the project progresses relative to its objectives.

PMP Exam Set B – Q27 ( PMBOK 6th edition )

As part of risk planning, some responses are designed for use only if certain events occur. A project manager of a multi-year project decided to trigger one such set of responses during the Monitor Risks process. Which of the following is likely to have triggered the responses?

A. Late receipt of status reports
B. A key employee going on vacation for three days.
C. Errors found in a deliverable document
D. Missing an intermediate milestone

D. Missing an intermediate milestone