PMP Exam Set G – Q65

You have just completed the first phase of a multi-phase project. You have performed the earned value measurements and found out that the current CPI is 0.79, the current SPI is 0.98. Your next phase plan should focus first on which element of the project?

A. Quality
B. Resources
C. Schedule
D. Cost

D. Cost

PMP Exam Set G – Q53

In a multi-phase project, the procurement team decided to close the procurements applicable to a particular phase of the project. What happens to unresolved claims?

A. Unresolved claims are usually resolved at the end of all phases of the project.
B. Unresolved claims are also closed when the procurements for that phase are closed.
C. Unresolved claims remain open for a period of 1 year from closure of procurements.
D. Unresolved claims may still be subject to litigation after closure.

D. Unresolved claims may still be subject to litigation after closure.