PMP Exam Set G – Q14 ( PMBOK 6th edition )

You have landed your dream job, as project manager working in an exotic sports car factory. Your project involves coming up with a smoother ride for the car. You have tasked the engineers to determine which type of suspension and what type of tires will provide the best ride and the most reasonable cost. This relates to which of the following processes?

A. Monitor Risks
B. Manage Quality
C. Control Quality
D. Plan Quality Management

D. Plan Quality Management

PMP Exam Set F – Q63 ( PMBOK 6th edition )

You are a project manager for KTmart and are currently engaged in a highly visible project. The company is about to implement an independent review to ensure that the project work is continuing to comply with the project’s policies, processes, and procedures. During which process would this review occur?

A. Close Project or Phase
B. Control Quality
C. Monitor Risks
D. Manage Quality

D. Manage Quality