PMP Exam Set F – Q4 ( PMBOK 6th edition )

A key output of Plan Resource Management is a list of project roles and responsibilities. What should this document include?

A. Work packages, Effort, Authority, Duties
B. Role, Responsibility, Authority, Risk
C. Role, Title, Resource Cost, Responsibility
D. Role, Authority, Responsibility, Competency

D. Role, Authority, Responsibility, Competency

PMP Exam Set D – Q96 ( PMBOK 6th edition )

How will an organization with a weak matrix organization structure affect the Plan Resource Management process?

A. The project manager will have no authority on the project.
B. The project manager will have a stronger role.
C. The project manager will have a relatively weaker role.
D. The project manager will have full authority.

C. The project manager will have a relatively weaker role.

PMP Exam Set D – Q69 ( PMBOK 6th edition )

A project manager has scheduled technical training for her project team members in order to increase their skills. During which of the following processes these trainings will be delivered to the team members?

A. Manage Quality
B. Acquire Resources
C. Develop Team
D. Plan Resource Management

C. Develop Team