PMP Exam Set C – Q25

A good quality audit should be:

A. structured and independent
B. informal and independent
C. informal and internal
D. structured and internal

A. structured and independent

PMP Exam Set B – Q94

You are in the execution stage of your project and you have been informed that “corporate” will be sending in a team of consultants to review whether your project activities comply with company’s and PMI’s policies, standards and procedures. This is an example of?

A. Quality Audit
B. Organizational Process Assets
C. Process Analysis
D. Recommended Corrective Actions

A. Quality Audit

PMP Exam Set B – Q3 ( PMBOK 6th edition )

In order to keep costs low, a project management team decided to apply statistical sampling while inspecting some of the work products. They decided to select 10 out of 50 engineering drawings for inspection. During which process should the sample frequency and sample size be determined?

A. Collect Requirements
B. Plan Quality Management
C. Control Quality
D. Manage Quality

B. Plan Quality Management

PMP Exam Set A – Q99

Select the best answer: Continuous process improvement reduces ___________ and ___________ , which allows processes to operate at increased levels of efficiency and effectiveness.

A. Process and policy overhead.
B. Departmental and organization processes
C. Cost and scope
D. Waste and non-value added activities.

D. Waste and non-value added activities.

PMP Exam Set A – Q97

A team of engineers is reviewing a scatter diagram to determine how the changes in two variables in a new type of automobile tire are related. The closer points on the diagram are to a diagonal line, ______________ .

A. the more likely a control group will be required
B. the more closely they are related
C. the less likely they are to be related
D. the less likely a control group will be required

B. the more closely they are related

PMP Exam Set A – Q92

A project manager used a control chart to determine whether a process was stable or not, and to determine if its performance was predictable. He determined the upper and lower specification limits based on the contractual requirements. A set of eighteen data points were taken. Of these, 8 consecutive data points were above the mean. What can you say about such a process?

A. A process is considered as out of control if five consecutive data points are above or below the mean. Hence the process is out of control.
B. A process is considered as out of control if six consecutive data points are above or below the mean. Hence the process is within control.
C. A process is considered as being within control if less than half the data points are above or below the mean. Hence the process is within control.
D. A process is considered as out of control if seven consecutive data points are above or below the mean. Hence the process is out of control.

D. A process is considered as out of control if seven consecutive data points are above or below the mean. Hence the process is out of control.

PMP Exam Set A – Q79

On a control chart, if six consecutive plot points are above the mean, then what can be established about the process?

A. The process is out of control
B. The process will be out of control after plotting the seventh point.
C. The process is in control
D. Nothing can be established

D. Nothing can be established