PMP Exam Set G – Q2

Jane is managing a complex industrial process reengineering project. She has identified all of her key project stakeholders and has conducted individual interviews with them to identify other project stakeholders as well. However, Jane is still not comfortable with her project’s stakeholders list as she believes there would be more key external stakeholders still missing from the list. What can help Jane in this situation?

A. Use stakeholder register templates from the organizational process assets.
B. Conduct more meetings with the key stakeholders.
C. Jane needs to get over her fear and finalize the project stakeholder register.
D. Seek expert judgment from subject matter experts.

D. Seek expert judgment from subject matter experts.

PMP Exam Set F – Q1 ( PMBOK 6th edition )

Jane has been assigned to establish a PMO in her organization. Jane believes that this project cannot be successful unless all of the key project stakeholders support the project. She also believes that she needs to pay special attention on stakeholder management to ensure success of this project. As the first step, she needs to develop her stakeholder register. Which of the following processes must be started by Jane to produce the project stakeholder register?

A. Plan Stakeholder Engagement
B. Monitor Stakeholder Engagement
C. Identify Stakeholders
D. Manage Stakeholder Engagement

C. Identify Stakeholders