PMP Exam Set F – Q73

The WBS is a deliverable-oriented hierarchical decomposition of the work to be executed by the project team, to accomplish the project objectives. This is created as part of:

A. Project Integration Management
B. Project Scope Management
C. Project Procurement Management
D. Project Schedule Management

B. Project Scope Management

PMP Exam Set E – Q42

________________ includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

A. Statement of Work
B. Project Schedule Management
C. Project Scope Management
D. Work breakdown structure

C. Project Scope Management

PMP Exam Set C – Q80

The Work Breakdown Structure (WBS) is a deliverable-oriented hierarchical decomposition of the work to be executed by the project team, to accomplish the project objectives and create required deliverables. The ‘Create WBS’ is a process under which Knowledge Area?

A. Project Schedule Management
B. Project Integration Management.
C. Project Scope Management
D. Project Cost Management

C. Project Scope Management

PMP Exam Set C – Q27 ( PMBOK 6th edition )

Which of the following activities fall under the planning process group but not under the Project Schedule Management?

A. Estimating the type of materials and equipment needed to perform project activities
B. Developing the Schedule Management Plan
C. Identification of various activities to produce the project deliverables
D. Developing a detailed description of the project and product being developed

D. Developing a detailed description of the project and product being developed