PMP Exam Set F – Q51

A project manager is looking at various classification methods to share information among project stakeholders. Which of the following correctly classifies the different methods used?

A. Pull communication – Meetings; Push communication – Newsletters; Interactive communication – E-learning repository
B. Interactive communication – Meetings; Push communication – E-learning repository; Pull communication – Newsletters
C. Push communication – Meetings; Pull communication – Newsletters; Interactive communication – E-learning repository
D. Interactive communication – Meetings; Push communication – Newsletters; Pull communication – E-learning repository

D. Interactive communication – Meetings; Push communication – Newsletters; Pull communication – E-learning repository

PMP Exam Set E – Q22

Sheila is a project manager managing a global project. She has stakeholders located in various parts of the globe. Due to the nature of the project, she also has large volumes of information that needs to be shared with the recipients. What type of communication method should she prefer for this purpose?

A. Pull communication
B. Push communication
C. Request based communication
D. Interactive communication

A. Pull communication

PMP Exam Set B – Q15

Jane is a project manager managing a global project. She has stakeholders located in various parts of the globe. Due to the nature of the project, she also has large volumes of information that needs to be shared with the recipients. What type of communication method should she prefer for this purpose?

A. Pull communication
B. Push communication
C. Request based communication
D. Interactive communication

A. Pull communication