PMP Exam Set F – Q6

In general, Perform Qualitative Risk Analysis is: _____________.

A. not often completed
B. complete and 100% accurate
C. in-depth and thorough
D. quick and cost-effective

D. quick and cost-effective

PMP Exam Set C – Q20

____________ is performed on risks that have been prioritized by the Perform Qualitative Risk Analysis process as potentially and substantially impacting the project.

A. Perform Risk Cost Analysis
B. Perform Risk Exposure Analysis
C. Perform Quantitative Risk Analysis
D. Perform Risk Outcome Analysis

C. Perform Quantitative Risk Analysis

PMP Exam Set A – Q33

__________ is performed on risks that have been prioritized by the Perform Qualitative Risk Analysis process as potentially and substantially impacting the project.

A. Perform Risk Cost Analysis
B. Perform Risk Exposure Analysis
C. Perform Quantitative Risk Analysis
D. Perform Risk Outcome Analysis

C. Perform Quantitative Risk Analysis