PMP Exam Set G – Q88

Midway through a project, a project manager determined that the project was running way behind schedule. If the project manager needs to shorten the project schedule, without changing the project scope, which of the following schedule compression techniques could be applied?

A. Crashing
B. Reserve Analysis
C. Forecasting
D. Last Tracking

A. Crashing

PMP Exam Set G – Q59

A project manager included contingency reserves and management reserves in the total budget of a high-risk project. He also made certain earned value measurement calculations. Which of the following is incorrect?

A. Contingency reserves are not part of the project cost baseline.
B. Management reserves are not part of the project cost baseline.
C. The project manager needs to get approval before spending management reserve.
D. Reserves are usually included in the total budget of a project.

A. Contingency reserves are not part of the project cost baseline.

PMP Exam Set F – Q76

A project manager is performing Reserve Analysis as a technique in one of the project management process that he is currently working on. Which of these is likely to be that process?

A. Estimate Reserves
B. Report Costs
C. Estimate Costs
D. Plan Costs

C. Estimate Costs