PMP Exam Set E – Q60

Nancy can bid on two projects. ‘Project A’ has a 50% return on investment, while the ‘Project B’ has 20% return on investment. The Project A’s scope of work is complex and Nancy’s organizations doesn’t have the necessary skills and experience to perform this project. However, Project B’s scope of work falls within the strengths of Nancy’s organizations. Which project must Nancy bid on?

A. None as this is a conflict of interest situation
B. Both since the overall profit will be higher
C. Project A since the return on investment is the highest
D. Project B since the organization has the required skills

D. Project B since the organization has the required skills