PMP Exam Set C – Q27 ( PMBOK 6th edition )

Which of the following activities fall under the planning process group but not under the Project Schedule Management?

A. Estimating the type of materials and equipment needed to perform project activities
B. Developing the Schedule Management Plan
C. Identification of various activities to produce the project deliverables
D. Developing a detailed description of the project and product being developed

D. Developing a detailed description of the project and product being developed

PMP Exam Set A – Q77

A project manager needed to shorten a project schedule. He decided to apply crashing, a schedule compression technique. Which of the following activities would not be an example of crashing?

A. Bringing in additional resources
B. Reducing project scope
C. Paying to expedite delivery activities
D. Approving overtime

B. Reducing project scope

PMP Exam Set A – Q2

Your manager has asked you to include the Human Resource Management Plan and the Schedule Management Plan in your Project Management Plan. Is this the appropriate place for these items?

A. No, these are stand alone documents only.
B. Yes, you should unquestioningly include anything your manager suggests.
C. No, these documents should not be created until later in the project.
D. Yes, include them in the Project Management Plan.

D. Yes, include them in the Project Management Plan.