PMP Exam Set B – Q58

Jane is an experienced project manager working on a pharmaceutical project. This project involves two big vendors to supply chemical products with specific composition for preparing drugs. While reviewing documents to see how the seller is performing, she noticed that some of the contractual terms were not met by the sellers. Since it is first time violation, she would like to initiate a corrective action to bring the performance of the seller consistent with the statement of work. Which of the following are NOT outputs of Jane’s effort?

A. Work performance data and approved change requests
B. Work performance information and change requests
C. Change requests and Organizational process assets update
D. Change requests and Project management plan updates

A. Work performance data and approved change requests

PMP Exam Set B – Q35

A project manager was involved in preparation of the project charter for an external project. One of the inputs to the project charter was a statement of work (SOW). The SOW may have been received from the customer as part of all of the following except:

A. As part of a request for information
B. As part of the business case
C. As part of a request for proposal
D. As part of a contract

B. As part of the business case