PMP Exam Set C – Q99 ( PMBOK 6th edition )

A project team is currently planning to perform the Monitor Stakeholder Engagement process to reassess the project stakeholders’ current engagement levels and review the current stakeholder management strategy. Which of the following is an output of this process?

A. Project documents updates
B. Information management system
C. Work performance data
D. Approved change requests

A. Project documents updates