PMP Exam Set G – Q91

A team of engineers is reviewing the architecture diagram for a new ERP system being deployed at a large accounting firm. The engineers are discussing the impact of the failure of each node in the diagram on overall availability of the final product. The intent of the discussion is to minimize the likelihood of failure and the effects of any failure. What is this called?

A. SWOT Analysis
B. Quantitative Analysis
C. Failure Mode and Effect Analysis
D. Deming Cycle

C. Failure Mode and Effect Analysis

PMP Exam Set F – Q88

You are meeting with your team, early in the project, and would like to address all the strengths, weakness, opportunities and threats the project is facing. What tool should be used?

A. SWOT Analysis
B. Interviewing
C. Delphi Technique
D. Brainstorming

A. SWOT Analysis

PMP Exam Set D – Q21

A team of engineers is reviewing the architecture diagram for a new ERP system being deployed at a large accounting firm. The engineers are discussing the impact of the failure of each node in the diagram on overall availability of the final product. The intent of the discussion is to minimize the likelihood of failure and the effects of any failure. What is this called?

A. SWOT Analysis
B. Quantitative Analysis
C. Failure Mode and Effect Analysis
D. Deming Cycle

C. Failure Mode and Effect Analysis