PMP Exam Set A – Q91

As part of EVM, a project manager is calculating the to-complete performance index (TCPI) based on EAC. The data that he has is: the budget at completion for the project is $ 100,000, the earned value for the project is $ 25,000, the actual costs to date are 40,000 and the estimate at completion is $ 115,000. What is the TCPI that he will obtain?

A. 1.1
B. 0.9
C. 1
D. 0

C. 1