PMP Exam Set B – Q41

Your company is way behind schedule in the deployment of a government mandated change to a health care processing system that must be in production by the end of the year. You and your team have met and decided to hire an additional 50 programmers to work with the existing staff on the activities in order to meet the due date. This is an example of what?

A. Resource Leveling
B. Fast Tracking
C. Crashing
D. Risk Transference

C. Crashing