(Program Evaluation and Review Technique) PERT | PERT = (P + 4M + O )/ 6
|
Standard Deviation (SD) | SD = P – O) / 6
|
Float/Slack | Late start – Early start Late finish – Early finish |
Communication Channels | n (n-1)/2
|
Cost Performance Index (CPI) | CPI = EV/AC
|
Schedule Performance Index (SPI) | SPI = EV/PV
|
Cost Variance (CV) | CV = EV – AC
|
Schedule Variance (SV) | SV = EV – PV
|
Estimate At Completion (EAC) | 1. BAC / CPI — if CPI remains the same
2. AC + ETC — Initial Estimates are flawed
3. AC + BAC – EV — if BAC remains the same
|
Estimate To Completion (ETC) | ETC = EAC -AC
|
Variance At Completion (VAC) | VAC = BAC – EAC
|