Which of the following is NOT a valid statement regarding the critical path method?
A. The early start and finish dates and late start and finish dates are calculated without factoring in resource limitations.
B. A forward pass and backward pass are performed through the project network paths.
C. The resulting late start and finish dates will be the project schedule baseline.
D. The flexibility of the schedule is measured by the difference between early and late dates.