Several of your resources report to another manager. You need them to participate in a series of project meetings over the next two weeks. How should you handle this?
A. Send meeting invitations to the project resources.
B. Provide a copy of the project charter to the other manager, showing that the resources on his team have been assigned to you for your project.
C. Request in advance resource participation from the other manager and the resources and communicate information about the timing and duration of the project meetings.
D. Shortly before each meeting, inform the other manager that his staff is required for your project meeting.