PMP Exam Set A – Q3

In a project that was yet to begin, many of the project team members were known in advance. This is called:

A. Proactive-planning
B. Skill-matching
C. Pre-assignment
D. Staffing-assignment

C. Pre-assignment
Tagged with 
Pre-assignment Proactive-planning project team Skill-matching Staffing-assignment
 

Post navigation

Previous Post« Previous PMP Exam Set A – Q2
Next Post PMP Exam Set A – Q4Next »
Testimonials
"I have passed my PMP exam! Really appreciate for this free resources. Practicing PMP questions on my mobile is so easy with this site."
— Kamal Shankar (India), Team Lead

"I found the PMP questions very realistic; I'm glad I found this site!"
— William Scott (Canada), Project Manager

"Thank you for the PMP questions and PMP formulas. Very useful for my exam preparation."
— Aaron Cranston (USA), SAP Consultant

"I am so happy I discover this website! Day one and I can't believe how much I have learned already. Thank you."
— Zico Farias (Brazil), IT Manager


We appreciate testimonials as well as any feedback from you. Please contact us here.
  • PMP Exam Useful Formulas
Copyright © 2025 Premium PMP Exam Questions
×Close