You are the project manager for a project and have just entered the third year of a scheduled four year project. You need to evaluate new risks that have emerged since the project began. What should you perform to provide this information?
A. Variance and trend analysis
B. Process Improvement Plan
C. Risk audit
D. Risk re-assessment