The project management team expects that during the course of the project, there could be delays in component delivery due to strikes, changes to the permitting processes or extensions of specific engineering durations. What analysis will help come up with contingency and response plans to mitigate these?
A. Contingency analysis
B. Variance analysis
C. What-If scenario analysis.
D. Schedule compression