PMP Exam Set A – Q77

A project manager needed to shorten a project schedule. He decided to apply crashing, a schedule compression technique. Which of the following activities would not be an example of crashing?

A. Bringing in additional resources
B. Reducing project scope
C. Paying to expedite delivery activities
D. Approving overtime

B. Reducing project scope