PMP Exam Set B – Q22

Which of the following is an output of the Define Activity process?

A. Milestone list
B. Project schedule activity diagrams
C. Resource calendar
D. Activity duration estimates

A. Milestone list
Tagged with 
Define Activity process duration estimates Milestone list Project Schedule Management Resource calendar
 

Post navigation

Previous Post« Previous PMP Exam Set B – Q21
Next Post PMP Exam Set B – Q23Next »
Testimonials
"I have passed my PMP exam! Really appreciate for this free resources. Practicing PMP questions on my mobile is so easy with this site."
— Kamal Shankar (India), Team Lead

"I found the PMP questions very realistic; I'm glad I found this site!"
— William Scott (Canada), Project Manager

"Thank you for the PMP questions and PMP formulas. Very useful for my exam preparation."
— Aaron Cranston (USA), SAP Consultant

"I am so happy I discover this website! Day one and I can't believe how much I have learned already. Thank you."
— Zico Farias (Brazil), IT Manager


We appreciate testimonials as well as any feedback from you. Please contact us here.
  • PMP Exam Useful Formulas
Copyright © 2025 Premium PMP Exam Questions
×Close