In order to keep costs low, a project management team decided to apply statistical sampling while inspecting some of the work products. They decided to select 10 out of 50 engineering drawings for inspection. During which process should the sample frequency and sample size be determined?
A. Collect Requirements
B. Plan Quality Management
C. Control Quality
D. Manage Quality