You have just taken over a project from another project manager about 6 months into a 12-month project. As you get to know the staff on the project, you become aware that 5 staff members are relatives of the previous project manager. What do you do?

A. Notify your project stakeholders there is a possibility that nepotism was behind some of the staffing decisions made on your project.
B. Check recruitment records of all employees
C. Report the HR manager to PMI.
D. Interview these 5 employees

A. Notify your project stakeholders there is a possibility that nepotism was behind some of the staffing decisions made on your project.