PMP Exam Set B – Q76

Jane, the project manager of a large project, found that she did not have the necessary number of resources required for some activities in the project. To account for the limited resources, she decided to apply the critical chain method. Which of the following would she use to protect the critical chain from slippage along the feeding chains?

A. Feeding buffers
B. Standby buffers
C. Overflow buffers
D. Dependent buffers

A. Feeding buffers