Your project is nearing completion, but a previously unidentified risk has been discovered and it could significantly affect one of the project deliverables. What do you do?
A. Transfer the risk.
B. Develop a risk mitigation plan.
C. Include the issue in the project risk log.
D. Notify the project stakeholders immediately.