PMP Exam Set B – Q96

A project team is currently assessing the project stakeholder management plan for its validity. The project documents are essential inputs to this process. Which of the following project documents must be used by the project team during this process?

A. All project documents prepared during the project so far.
B. Project documents prepared during the project planning.
C. Project documents prepared during the project execution.
D. Project documents prepared during the project initiation.

A. All project documents prepared during the project so far.