PMP Exam Set C – Q15

What do buyers and seller have in common with regards to Control Procurements?

A. Each party ensures that both it and the other party meet their contractual obligations and that their own legal rights are protected.
B. Both parties have specific resources that can be idle.
C. Both parties have a contract change management plan.
D. Each party has its own project plan and legal team

A. Each party ensures that both it and the other party meet their contractual obligations and that their own legal rights are protected.