PMP Exam Set C – Q58

You are setting up your project team and you are looking at a chart that shows that the programming will be performed by Systems Development, the infrastructure will be implemented by Infrastructure Systems, the customer communication will be handled by the Call Center. This is an example of what type of chart?

A. RACI
B. Organizational Breakdown Structure (OBS)
C. Work Breakdown Structure
D. Resource Breakdown Structure (RBS)

B. Organizational Breakdown Structure (OBS)