As the project manager of a high-visibility project, you are in the process of Identifying risks. You are concerned that the data you collect might be biased. A technique that helps keep the bias out of the data and keeps any one person from having undue influence on the outcome is:
A. Interviewing
B. Round-robin technique
C. Ishikawa technique
D. Delphi technique