You are a Project Manager for a company that designs and develops automation systems for car companies. You are in the Close Project process for a project in which a new automation system has been designed and created for a car company located in Korea. You need to obtain formal acceptance for the new automation system. All of the following statements are true with respect to the final acceptance of the new system EXCEPT?
A. Performance tests on the new automation system should be completed by the car company.
B. A formal statement is issued indicating that the new automation system meets the terms of the contract.
C. Final acceptance for the new automation system can be informal or formal.
D. A checklist can be used to determine whether the new automation system meets the car company’s specifications