PMP Exam Set C – Q72

Your organization has recognized a need to replace the legacy manufacturing system with a modern software application to reduce delivery delays and process downtime. Your IT director anticipates a project to fulfill this business need, however, he warns that the new project’s budget cannot exceed $75,000 due to shortages in the department budget. He also indicates that no additional staff will be allocated to this project other than the existing IT staff. If you are assigned as a project manager to this project, you would document these initial project conditions as:

A. Project assumptions in the project charter
B. Project restrictions in the project management plan
C. Project constraints in the project charter
D. Project conditions in the project cost management plan and human resource management plan

C. Project constraints in the project charter