All team members have not yet been acquired for a project. However, the project manager went ahead with estimating activity durations, budgeting and other activities. What could likely happen to the activity durations?

A. The activity durations are likely to decrease.
B. The activity durations are likely to change.
C. The activity durations will remain the same.
D. The activity durations are likely to increase.

B. The activity durations are likely to change.