PMP Exam Set C – Q89

To communicate with stakeholders on the resolved issues and the issues that are hard to resolve, you use an issue log in your project. Since you assign an owner for every issue and resolve it by proactively working on it, your stakeholders actively support all your efforts in managing the project. This method of actively resolving issues and reducing risks to the project is known as:

A. Quality management
B. Scope Management
C. Communications management
D. Stakeholder management

D. Stakeholder management