PMP Exam Set C – Q96

You are the Project Manager for Commodities, Inc. You are involved in a new project to create an internal web site for the employees of Commodities, Inc that will allow them to view events within the company. All of the following options listed are project constraints EXCEPT?

A. The project must be completed by December 31st of the current year.
B. There is a budget of $75,000 for the project.
C. The navigation menu for the website must be on the top of the page.
D. Only 3 employees are available to work on the project.

C. The navigation menu for the website must be on the top of the page.