PMP Exam Set D – Q13

You are decomposing your WBS into smaller pieces of work. What is one item that does NOT describe how far the work should be decomposed?

A. Until it can be realistically estimated
B. Can’t be subdivided any further
C. Until a meaningful conclusion
D. Cannot be decomposed more than 10 levels

D. Cannot be decomposed more than 10 levels